Earned Value Management

Variances

SV = BCWP – BCWS = EV – PV

CV = BCWP – ACWP = EV – AC

VAC = BAC – EAC

CVP% = CV/BCWP = CV/EV

SVP%= SV/BCWS = SV/PV

Indicators

CPI = BCWP/ACWP = EV/AC

SPI = BCWP/BCWS = EV/PV

Estimates

EAC = (ACWP/BCWP) * BAC = (AC/EV) * BAC = BAC/CPI

ETC = EAC – ACWP = EAC – AC

Other

EV = BCWP = (% complete) * BAC

% complete = BCWP/BAC = EV/BAC

% money spent = ACWP/BAC = AC/BAC

New project length = original length /CPI