Formulas y Notas Útiles para Project Manager: Tecnicas de Valor Ganado EVM
Friday, June 8th, 2007 at
1:52 pm
Earned Value Management
Variances
SV = BCWP – BCWS = EV – PV
CV = BCWP – ACWP = EV – AC
VAC = BAC – EAC
CVP% = CV/BCWP = CV/EV
SVP%= SV/BCWS = SV/PV
Indicators
CPI = BCWP/ACWP = EV/AC
SPI = BCWP/BCWS = EV/PV
Estimates
EAC = (ACWP/BCWP) * BAC = (AC/EV) * BAC = BAC/CPI
ETC = EAC – ACWP = EAC – AC
Other
EV = BCWP = (% complete) * BAC
% complete = BCWP/BAC = EV/BAC
% money spent = ACWP/BAC = AC/BAC
New project length = original length /CPI